Progress continues. Some of the windows are in, the roof is covered with a waterproofing membrane things are dry inside. The front deck is framed. The HVAC people have installed the gas line, I'm working on the fresh air and exhaust ducts. The plumber is about 1/2 done and I'm about 33% done with the electrical. A bunch of inspections are coming up and then insulation and drywall can begin.
Here are the latest pics.
|
Front deck framed and a couple of windows are in |
|
Basement bedroom window |
|
Gas line for the boiler |
|
powder bath waste lines |
|
Master bath sinks |
|
Windows from the inside |
|
Recessed lighting in kitchen and island pendant rough in |